Botswana’s abandoned projects leave taxpayers holding the bill

Admin3 hours ago15719 min

Across Botswana, the skeletons of unfinished promises are easy to find. A school expansion that was supposed to open its doors years ago. A hospital that cannot yet admit the sick. A pipeline meant to carry water to households still waiting at dry taps. Each was financed with public money. Each, in its own way, has become a monument not to progress but to the widening gap between what the state pays for and what it ultimately receives.

The country’s public infrastructure has slid into a crisis that is no longer really about concrete and steel. It is about trust – about how government contracts are awarded, managed and policed, and why schools, roads, hospitals and water systems so often collapse into a familiar tangle of delays, ballooning costs and payments that nobody can quite explain. Audit after audit and inquiry after inquiry keep arriving at the same uncomfortable door: not simply why these projects stall, but why the identical weaknesses resurface year after year, long after everyone has agreed they must be fixed.

The dimensions of the problem are laid bare in the findings of Parliament’s Public Accounts Committee, which reported that government accounts had drawn qualified audit opinions for seven straight years – a streak that speaks less to isolated error than to habit. The committee catalogued a now-wearily familiar litany: contractors overpaid, consultancy fees inflated without authorization, and senior officials who approve payments in defiance of public finance rules yet seem to face no real reckoning. It is a system, the findings suggest, in which flaws survive long after they are named, quietly eroding any confidence that the state can guard the public purse.

To test whether the paperwork matches the pavement, the committee has called for on-site inspections of the country’s marquee projects: the North-South Carrier pipeline from Mmamashia to Kanye, the Gumare-Sepopa and Sepopa-Mohembo roads, Maun Secondary School, the Nata-Francistown road, Nyangabwe Hospital and Tonota College of Education. The exercise is designed to reveal whether physical progress actually corresponds to the glowing figures in official reports – whether the money committed, the work completed and the services delivered are three versions of the same truth, or three separate stories. Yet inspections, on their own, resolve nothing. Their worth will depend entirely on whether what they uncover is followed by explanation, correction and consequence.

Nowhere is the arithmetic more startling than at the Kanye Water Sanitation Project. Its original contract value of P707 million reportedly swelled to P3.4 billion – an escalation of roughly P2.7 billion, pushing the revised figure to nearly five times the original. Cost overruns do not, by themselves, prove wrongdoing; infrastructure is a messy business, and genuine engineering, design and site surprises can legitimately drive up a bill. But a jump of this magnitude, attached to water infrastructure a community cannot do without, demands a far more detailed public accounting than it has received – of how the first estimate was built, why it required such a dramatic rewrite, and whether the extra billions rested on solid technical and financial ground.

Smaller projects echo the pattern on a more modest scale. The Tswapong South Phase II water project climbed from about P291.4 million to P334.8 million, a rise of roughly P43.3 million. In another water-related case, consultancy fees crept from P23.4 million to P35.5 million – an unauthorized increase of some P12 million. Each raises the same quiet, corrosive doubt: how robust were the initial assessments, who signed off on the variations, and can the institutions responsible actually stop spending from breaching its approved ceiling? Where the reasons go undocumented and unexamined, taxpayers are offered no assurance that their money is being spent with care.

The education sector tells the story in human terms. The Ministry of Basic Education disbursed P703 million for maintenance and expansion at 33 junior secondary schools during the 2018/19 and 2019/20 financial years, with cost overruns of roughly P16 million identified across five of them. In one case, a school expansion worth about P65.2 million was meant to be finished within 504 days, by October 27, 2017. By the time auditors arrived, it had consumed 966 days and some P72.5 million – along with about P2.5 million in overpayments, including inflated claims tied to extensions of time. In another, a project stood only 80 per cent complete despite having absorbed P23.8 million, or 94 per cent of its contract sum. The implication is unsettlingly simple: public institutions appear to be paying contractors faster than those contractors are building.

The toll does not stay confined to a ledger. A delayed school means crowded classrooms and interrupted learning. An unfinished hospital means care deferred. A stalled road raises transport costs and strands businesses, while incomplete water works leave households dry even after their taps were, on paper, already paid for. In a tight fiscal climate, every pula poured into a troubled project is a pula not spent on medicine, school repairs, jobs programmes or the next piece of infrastructure. The real price of a stalled project, then, is not merely its revised contract value – it is the growing pile of benefits a community forfeits while it waits.

The Public Procurement Regulatory Authority has pointed to the usual suspects: weak procurement planning, thin institutional capacity, and the glaring absence of an electronic procurement system. Its chief executive, Tumelo Motsumi, adds poor supervision and shaky contract management to the charge sheet. The authority says it investigated 23 procurement complaints in the last financial year, suspended 43 contractors for fraudulent conduct and blacklisted eight companies. But it does all this with a staff of five – a skeleton crew expected to patrol procurement across a sprawling government. The numbers invite their own blunt question: can oversight this under-resourced possibly catch risk before it hardens into expensive failure?

The remedy must reach beyond the ritual of naming problems and ordering officials to take action. Real oversight means a transparent system that tracks every major project from tender and award through every variation, payment, completion and handover. A publicly accessible register of stalled projects should lay out the original contract value, the revised cost, the contractor, the start date, the promised finish, the money already paid, the share of work done and the reasons for delay. Significant variations should come with documented justification and independent technical review; payments should be bolted to verified progress. Where investigators establish overpayment, negligence or misconduct, the law’s disciplinary, civil and criminal machinery should follow. Contractors must answer for their failures – and officials should not slip free simply because the damage flowed through a government department.

In the end, Botswana’s infrastructure problem is not a story about unfinished buildings, late roads or runaway water budgets. It is a test of whether the state can turn expenditure into working assets and real services while keeping faith with the people who paid. Repeated audits have proven that identifying a weakness is not the same as curing it. The committee’s proposed inspections offer a genuine chance to establish the true condition of these troubled projects – but only if their findings are made public and matched by measurable repair. Absent stronger contract controls, honest reporting, properly funded oversight and credible consequences, the country will keep buying infrastructure that arrives late, costs more than promised, or never delivers at all. Taxpayers deserve more than a well-argued explanation of what went wrong. They deserve proof that it is being put right.

That demand points to the deeper fault line beneath the rubble: the stubborn distance between spotting a financial irregularity and actually stopping it from happening again. The committee’s findings on qualified opinions, unauthorized fee increases and contractor overpayments cannot be filed away as isolated clerical slips; they beg a harder look at the institutional conditions that let such errors take root and flourish. The Kanye project matters precisely because a leap from P707 million to P3.4 billion cannot be waved through – it demands a full account of the original assumptions, the scope of the changes, the approvals granted and the link between money spent and work delivered. Inflation, redesigns and unforeseen ground conditions can all legitimately raise a cost, but they must be shown through transparent documentation, not simply asserted. The same logic governs the schools where spending has nearly consumed the contract before the building is done: paying heavily against incomplete work raises pointed questions about whether certification, progress checks and contractual safeguards are working at all.

The fiscal stakes sharpen the picture. In a nation still tethered to the swings of diamond revenue and facing mounting pressure on its finances, every needless variation, every avoidable delay, every unsupported payment quietly drains money from somewhere it is needed more. Honest accountability, though, requires precision. A cost overrun, an irregular payment, a stalled project and a proven loss from misconduct are not the same thing, and treating them as interchangeable only lets allegation outrun evidence. An overrun may reflect a legitimate change in scope; an unauthorized payment may breach procedure without amounting to a crime. It matters, too, whether the figures quoted across different audit years describe today’s costs or yesterday’s findings, whether revised values already include approved changes, and whether sums flagged as overpayments have since been clawed back. Without that verification, an accountability story risks splicing together numbers that do not belong side by side, or dressing up old findings as the present state of play.

Capacity sits at the heart of it. The procurement authority’s reported staffing squeeze and the missing electronic system mean that thousands of transactions are being watched by a handful of people working from scattered records – fertile ground for irregularities to pass unnoticed. Yet more staff and better software will matter only if they rest on enforceable rules, independent verification, open contract data and a clear line of responsibility for acting on what audits reveal. Parliament, too, must make its oversight amount to more than site visits and hearings. Every troubled project should carry a documented action plan – the outstanding work, the responsible institution, the revised deadline, the financial exposure and the steps taken to address any established breach. Follow-up reports should show whether recommendations were carried out, money recovered and projects finished to standard. That alone would convert oversight from an autopsy into something capable of preventing the next death.

The gravest danger exposed by Botswana’s infrastructure record may be the quiet normalization of failure – the slow slide by which financial irregularities become routine audit entries rather than triggers for reform. Scrutiny is valuable, but scrutiny that changes nothing is merely expensive theatre. The government should be made to account not only for the money it spends, but for the assets it delivers, the services it makes available and the corrective action it takes when funds are mishandled. The decisive test is simple to state and hard to meet: can a project’s final cost be justified, its quality independently verified and its promised benefits delivered to the people it was built for? Until that becomes the rule rather than the exception, Botswana’s taxpayers will keep carrying a double burden – financing the nation’s infrastructure, and then paying again, in money and in missed opportunity, each time that infrastructure arrives late, half-built or dearer than it ever needed to be.