Contractor unreachable as P376 Million Moshupa–Manyana road project stalls

Admin15 minutes ago675 min

Construction of the Moshupa–Manyana road has ground to a halt, and the Moshupa District Council has been unable to reach the contractor, council chairperson Peter Sethibe told a Full Council meeting this week.

“Honourable councillors, I must report with concern on the Moshupa–Manyana project. The project is currently 47% complete, and it has since come to a standstill. There is no work on the ground, and we are unable to reach the contractor,” Sethibe said in his opening address.

The 33.5-kilometre road project was awarded to Heinsite Construction in 2024. It was expected to ease congestion on the A10 by providing another route from Moshupa through Manyana and Mmakgodi towards Gaborone. A separate link from Manyana was also intended to give motorists access to the capital via Boatle and the Boatle–Game City interchange.

The project has now missed its planned completion date of 17 October 2026.

The warning signs were already apparent in July. Responding to a parliamentary question on 29 July, Assistant Minister for Transport and Infrastructure Keoagile Atamelang said construction was 10 months behind schedule. Physical progress stood at 42%, against a planned 79%.

Atamelang attributed part of the delay to difficulties obtaining a mineral permit. Until a permit for a nearby borrow pit was granted on 13 July 2026, the contractor had to haul construction material from a private pit 12 kilometres away. The longer journey slowed work on site, he said.

Heavy rain during the 2024, 2025 and 2026 rainy seasons had cost the project a further 52 days. The contractor had submitted a notice of intention to claim an extension of time because of the weather-related delays.

The assistant minister also pointed to the contractor’s financial difficulties. Because progress was slower than anticipated, its interim payment certificates were for less than the minimum amount set out in the contract, putting pressure on cash flow. At the time, the government had paid P92,741,602.39 towards the project’s stated contract value of about P376.4 million. Atamelang said the ministry was processing the payments to help the contractor maintain cash flow and still expected the project to be completed within budget.

The contractor had also been issued a notice to accelerate work and recover lost time, Atamelang said. He was responding to Moshupa–Manyana MP Karabo Gare, who had asked for an update on construction progress and whether the road would be finished by its scheduled deadline.

In other council business, Sethibe said the Setlhomo Edison Masisi Primary Hospital was complete and due to be handed over on 30 November 2026.

“For too long, this house has heard the same figure – 99% – reported at Full Council after Full Council. Today, I can come with a different number,” he said. Once the handover is complete, the Ministry of Health intends to begin operating the hospital in phases.

Sethibe also reported that an investigation into the A10 bridge, which has collapsed twice, was complete. The consultant’s findings and designs are being assessed before the Ministry of Transport and Infrastructure begins the process of appointing a contractor.